OPTIMASI STRUKTUR ATAP TAHAP 1-4 BAJA WF DAN KOMBINASI WF SPACE FRAME TERHADAP BIAYA DAN WAKTU(STUDI KASUS: PROYEK PEMBANGUNAN ISLAMIC CENTER JAMBI)

Authors

  • Indah Puspita Dewi Universitas Jambi Author
  • Ade Nurdin Universitas Jambi Author
  • Putri Nurul Kusum Whardani Universitas Jambi Author

DOI:

https://doi.org/10.69714/f5a17483

Keywords:

WF Steel Structure, Space Frame , Optimization , Cost Time

Abstract

The roof structure of the Islamic Center Jambi building was initially planned entirely with Wide Flange (WF) steel. However, due to time limitations and tower crane capacity, stages 2–4 were redesigned into a Space Frame system to accelerate construction. This study aimed to analyze the cost and time comparison between a full WF structure (stages 1–4) and a WF–Space Frame combination (WF stage 1, Space Frame stages 2–4). Cost analysis was based on the 2023 Public Works Unit Price Analysis (AHSP), while scheduling was evaluated using the Critical Path Method (CPM). Results showed that the WF–Space Frame combination reduced costs by 11.989% (IDR 35.308 billion vs. 40.118 billion) and shortened project duration by 64 days (348 vs. 412). Therefore, the WF–Space Frame system proved more efficient in both cost and time, making it a more optimal alternative.

References

Alfandias Seysna Putra1 Ii Maryadi, Yudhistira P.R, Ibnu Rizal, R. A. . (2021). TINJAUAN PERBANDINGAN RENCANA ANGGARAN BIAYA ATAP MENGGUNAKAN RANGKA KAYU DAN RANGKA BAJA RINGAN. 7(1), 23–29.

Badan Standarisasi Nasional. (2002). SNI 03-1729-2002. Tata Cara Perencanaan Struktur Baja Untuk Bangunan Gedung, 215.

Ferdiansyah, B. V., Setyaning, L. B., & Aziz, U. A. (2024). Jurnal Anggapa Analisis Penjadwalan Proyek Dan Rencana Anggaran Biaya ( RAB ) Dengan Critical Path Method ( CPM ) Studi Kasus : Proyek Pelebaran Jalan Ayah – Jladri Paket 2. 3(November), 1–10.

Fikri, M. (2023). Analisa Perbandingan Harga Satuan Pekerjaan Rangka Atap Baja Ringan dengan Rangka Atap Kayu. Jurnal Ilmiah Ecosystem, 23(3), 646–657. https://doi.org/10.35965/eco.v23i3.3792

Firdausi, N. I. (2020). STUDI PENERAPAN CRITICAL PATH METODE (CPM) PADA PROYEK PEMBANGUNAN PABRIK SEMEN REMBANG PT SEMEN GRESIK Wasito. Kaos GL Dergisi, 8(75), 147–154. https://doi.org/10.1016/j.jnc.2020.125798%0Ahttps://doi.org/10.1016/j.smr.2020.02.002%0Ahttp://www.ncbi.nlm.nih.gov/pubmed/810049%0Ahttp://doi.wiley.com/10.1002/anie.197505391%0Ahttp://www.sciencedirect.com/science/article/pii/B9780857090409500205%0Ahttp:

Hadicara, D. (2023). Penerapan Metode Pert Dan Cpm Pada Pembangunan Jalan Tinjomoyo – Sekaran. Program Magister Teknik Sipil Fakultas Teknik Universitas Islam Sultan Agung Semarang.

Hidayat. (2020). Studi analisis Struktur Space frame Double Layer Barel Vaults dan Flat Cover. Universitas Muhamadiah Sumatra Utara, 1–123.

Hikmah, N. (2019). ANALISIS PERBANDINGAN METODE PELAKSANAAN STRUKTUR RANGKA ATAP BAJA KONVENSIONAL DAN STRUKTUR RANGKA ATAP SISTEM SPACE FRAME DARI SEGI BIAYA DAN WAKTU (Studi Kasus : Proyek Perluasan Terminal Bandara Sultan Thaha Jambi).

Husnah, H., Darfia, N. E., & Hidayat, F. (2019). Analisis Struktur Rangka Baja Ringan Dan Baja Berat (Wf) Dengan Metode Bricscad Dan Metode Elemen Hingga. Siklus : Jurnal Teknik Sipil, 5(2), 87–96. https://doi.org/10.31849/siklus.v5i2.3232

Indra Khaidir, Embun Sari Ayu, & Mutiara Dwi Putri Andriani. (2022). Implementasi Metode Precedence Diagram Method (Pdm) Dalam Pengendalian Proyek Konstruks. Jurnal Rekayasa, 12(2), 175–182. https://doi.org/10.37037/jrftsp.v12i2.136

Leksono, B., Nugroho, D., & Yanti, E. I. (2020). Optimasi Waktu Pelaksanaan Pembangunan Ruang Praktik Siswa SMK Negeri 1 Duduksampeyan dengan Metode PERT. Jurnal Keilmuan Dan Terapan Teknik, Vol 9(2), 49–61.

Mahendra, M. Y., & Oetomo, W. (2023). Analisis Biaya dan Waktu Menggunakan Crashing Method pada Proyek Peningkatan Jalan Banyakan-Tiron Kediri. Jurnal Teknik Sipil, 15(2), 89–101.

Manurung, E. H., Prajoko, A., Sitohang, O., & Haryanto, H. (2023). Analisis Biaya dan Waktu Pekerjaan Konstruksi Struktur Rangka Atap Baja Portal Frame dan Portal Truss. Jurnal Rekayasa Konstruksi Mekanika Sipil (JRKMS), 6(1), 31–39. https://doi.org/10.54367/jrkms.v6i1.2557

Menteri Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia. (2023). AHSP CIPTA KARYA. Surat Edaran Direktur Jenderal Bina Konstruksi Nomor 73/SE/Dk/2023 Tentang Tata Cara Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum Dan Perumahan Rakyat, 1–860. https://binakonstruksi.pu.go.id/produk/produk-hukum/surat-edaran-direktur-jenderal-bina-konstruksi-nomor-73-se-dk-2023/

Nofendi Saputro, Ir. Dian Arumningsih DP., M.T., Kusdiman Joko Priyanto, S.T., M. T. (n.d.). STRUKTUR SPACE FRAME SEBAGAI KOMPONEN PEMBENTUK ESTETIKA PADA PERENCANAAN TRIBUN SIRKUIT MIJEN DI DESA TAMBANGAN KECAMATAN MIJEN KOTA SEMARANG PROVINSI JAWA TENGAH.

Rahmania, A. (2021). Struktur Space frame sebagai Komponen Pembentuk Estetika pada Perancangan Gedung Pusat Seni Budaya Jawa Barat, di Bandung. AGORA:Jurnal Penelitian Dan Karya Ilmiah Arsitektur Usakti, 18(2), 60–68. https://doi.org/10.25105/agora.v18i02.7487

Rizmolayasar, L. D., Susetyarto, M. B., & Rosnarti, D. (2023). Penggunaan Struktur Space frame Sebagai Elemen Estetika Pada Bangunan Cultural Center Di Berbagai Negara. Metrik Serial Teknologi Dan Sains, 4(2), 68–75. http://publikasi.kocenin.com/index.php/teksi/article/view/472

Sunanta, N. , W. G. , S. A. (2023). Analisis Perbandingan Biaya Dan Waktu Pembangunan. ANALISIS PERBANDINGAN BIAYA DAN WAKTU PEMBANGUNAN KONSTRUKSI KAP BAJA RINGAN DENGAN KAP KAYU (Studi Kasus: Private Villa Kedungu, Kediri, Tabanan), 12(1), 2–19.

Wicaksono, A. B., & Setiawan, B. (2023). Analisa Pengendalian Waktu Menggunakan Metode Critical Path Method (Cpm) Pada Proyek Struktur Rangka Atap Baja Stasiun Kcic Karawang. Jurnal Darma Agung, 31(3), 50. https://doi.org/10.46930/ojsuda.v31i3.3330

Downloads

Published

2025-10-09

How to Cite

OPTIMASI STRUKTUR ATAP TAHAP 1-4 BAJA WF DAN KOMBINASI WF SPACE FRAME TERHADAP BIAYA DAN WAKTU(STUDI KASUS: PROYEK PEMBANGUNAN ISLAMIC CENTER JAMBI) (Indah Puspita Dewi, Ade Nurdin, & Putri Nurul Kusum Whardani , Trans.). (2025). Jurnal Ilmiah Multidisiplin Ilmu, 2(5), 186-192. https://doi.org/10.69714/f5a17483